TY - JOUR
T1 - Cost estimation model for semiconductor hookup construction projects
AU - Wen, Chao Pao
AU - Hsiao, Fan Yi
AU - Wang, Shih Hsu
AU - Wang, Wei-Chih
AU - Yu, Wen Der
PY - 2013/1/1
Y1 - 2013/1/1
N2 - Hookup construction is one of the major tasks for a semiconductor facility construction project. The data required for conducting cost estimations of the hookup construction task are often incomplete because the whole project is undertaken in a short time or in a fast-track situation. Consequently, poor cost estimation is very likely resulted. Properly predicting the cost of a hookup construction project is crucial to control the total cost of a whole facility project. Thus, this study proposes a new cost estimation method for semiconductor hookup construction by integrating three existing approaches, including component ratios, fuzzy adaptive learning control network (FALCON), and fast messy genetic algorithm (fmGA). The proposed model is applied to 27 case projects. The results show that the average accuracy rate of the cost estimations for these case projects is around 84.85%. The accuracy rate of the proposed model has increased for about 6.07%~14.83% when comparing to those calculated by the conventional averaging method, the component ratios method and regression analysis method, respectively.
AB - Hookup construction is one of the major tasks for a semiconductor facility construction project. The data required for conducting cost estimations of the hookup construction task are often incomplete because the whole project is undertaken in a short time or in a fast-track situation. Consequently, poor cost estimation is very likely resulted. Properly predicting the cost of a hookup construction project is crucial to control the total cost of a whole facility project. Thus, this study proposes a new cost estimation method for semiconductor hookup construction by integrating three existing approaches, including component ratios, fuzzy adaptive learning control network (FALCON), and fast messy genetic algorithm (fmGA). The proposed model is applied to 27 case projects. The results show that the average accuracy rate of the cost estimations for these case projects is around 84.85%. The accuracy rate of the proposed model has increased for about 6.07%~14.83% when comparing to those calculated by the conventional averaging method, the component ratios method and regression analysis method, respectively.
KW - Cost estimation
KW - Fast messy genetic algorithms (fmGA)
KW - Fuzzy adaptive leaning control network (FALCON)
KW - Semiconductor hookup construction
UR - http://www.scopus.com/inward/record.url?scp=84897507966&partnerID=8YFLogxK
U2 - 10.6652/JoCICHE.201312_25(4).0002
DO - 10.6652/JoCICHE.201312_25(4).0002
M3 - Article
AN - SCOPUS:84897507966
SN - 1015-5856
VL - 25
SP - 273
EP - 282
JO - Journal of the Chinese Institute of Civil and Hydraulic Engineering
JF - Journal of the Chinese Institute of Civil and Hydraulic Engineering
IS - 4
ER -